Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Boiler drawing
Stokers
Ash handling system
Burners
Dampers, stacks and breechings
Fuel oil equipment
Piping and specialty items
Flexible ball expansion joint installation details
Reinforced concrete foundation
Reproducible drawings
Submit for approval within [60] [75] [90] days after award of
contract. Drawing size shall be A1 (841 by 594 mm) 34 by 22 inches.
SD-03 Product Data
Boiler
Stacks
Insulation
Submit for approval within [60] [75] [90] days after award of
contract.
SD-04 Samples
SECTION 15502N
Page 44