instructions and recommendations, that the unit or system has been run,
rotating parts have been dynamically balanced, fluid (including air) flows
adjusted and have been calibrated, and the sub-system (or equipment) is
ready for final testing, before entire boiler plant may be given an
acceptance test.
1.6.6.4
Submit four copies of the certified record.
1.6.6.5
Backflow Preventer
Submit a Certificate of Full Approval or a current Certificate of Approval
for each design, size, and make of backflow preventer being provided for
the project.
1.6.7
1.6.8
Operation and Maintenance Data
Submit operation and maintenance data for each equipment, including control
components. Include the following supplemental information in addition to
requirements of Section 15050N BASIC MECHANCIAL MATERIALS AND METHODS.
a.
Illustrations, catalog information, shop drawings, and certified
drawings of each item of equipment and control components
b.
Tests and test results
c.
Adjustments
d.
Fan and blower characteristics curves
e.
Pump characteristic curves superimposed on system curves at
various pumping rates (20, 40, 60, 80, 100 percent capacity)
f.
Boiler predicted performance data
g.
List of special tools required
1.7
DELIVERY, STORAGE AND HANDLING
1.7.1
Assembly of Components
Each assembly of components packaged as a unit shall be of the size that
can be transported by common carrier without disassembly insofar as
shipping clearances are concerned.
1.7.2
Storing Tubes
Grind tube ends before shipment and properly coat against elements that may
cause rusting or decomposition prior to erection. Store tubes used in
erection of boiler with full protection from elements and at no time shall
tubes be stored upon the ground. Maintain sufficient space between bottom
row of tubes and ground to give good circulation of air at all times.
Before installing tubes, remove mill scale and other foreign matter.