indicated on the drawings. Except as modified herein, the system shall
meet the requirements of NFPA 11, NFPA 13, NFPA 16, NFPA 24 and NFPA 72.
1.4
SYSTEM OPERATIONAL FEATURES
**************************************************************************
NOTE:
General operation of the system should be
described here. This description is not intended to
replace a controls matrix or sequence of operation
otherwise required or provided on the drawings.
**************************************************************************
[The wet-pipe sprinkler system shall operate so that actuation of a single
sprinkler will cause water to flow through the alarm check valve, foam
concentrate to enter the affected proportioners, and foam-water solution to
be discharged from actuated sprinklers and the nozzle system.] [The
single-interlocked preaction sprinkler system (without supervisory air)
shall operate so that actuation of a single heat detector or manual release
will cause the automatic water control (deluge) valve to open, foam
concentrate to enter the affected proportioners, and foam-water solution to
be discharged from actuated sprinklers and the nozzle system.] [The deluge
sprinkler system shall operate so that actuation of a single heat detector
or manual release will cause the automatic water control (deluge) valve to
open, foam concentrate to enter the affected proportioners, and foam-water
solution to be discharged from all sprinklers on the system and the nozzle
system.]
1.5
SUBMITTAL PREPARER'S QUALIFICATIONS
The fire protection system submittals, including as-built drawings, shall
be prepared by an individual who is either a registered professional
engineer with ten years experience designing AFFF systems or who is
certified as a Level IV Technician by National Institute for Certification
in Engineering Technologies (NICET) in the Automatic Sprinkler System
Layout subfield of Fire Protection Engineering Technology in accordance
with NICET 1014-7.
1.6
INSTALLER'S QUALIFICATIONS
The installer shall be experienced and regularly engaged in the
installation of the type and complexity of fire protection system included
in this project. A statement prior to submittal of any other data or
drawings, that the proposed installer is regularly engaged in the
installation of the type and complexity of system included in this project
shall be provided. In addition, data identifying the locations of at least
three systems recently installed by the proposed installer which are
comparable to the system specified shall be submitted. Contractor shall
certify that each system has performed satisfactorily, in the manner
intended, for a period of not less than 6 months.
1.7
REGULATORY REQUIREMENTS
The advisory provisions of NFPA standards and recommended practices
specified shall be considered mandatory, as though the word "shall" had
been substituted for "should" wherever it appears. In the event of a
conflict between referenced NFPA standards and this specification, this
specification shall govern. Reference to "authority having jurisdiction"
shall be interpreted to mean the Contracting Officer.