IDS operational test plan; G
Installer's qualifications; G
Instructor's qualifications; G
IDS equipment; G
SD-10 Operation and Maintenance Data
IDS, Data Package 5; G
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA.
SD-11 Closeout Submittals
1.6
QUALITY ASSURANCE
1.6.1
Drawings
1.6.1.1
IDS Components
Provide drawings that clearly and completely indicate the function of each
component of the IDS. Indicate termination points of devices and indicate
interconnection between modules and devices. In addition, provide a layout
drawing which shows spacing of components, location, and details of
mounting and positioning.
1.6.1.2
Overall System Schematic
The overall system schematic shall indicate the sequence of operation, the
relationship of integrated components on one diagram, and show power
source, system controls, impedance matches, plus number, size,
identification, and maximum lengths of interconnecting wires. Drawings
shall not be less than [420 by 297 mm] [_____] mm [11 by 17 inches] [_____]
inches.
1.6.2
Experience and Qualifications
1.6.2.1
Installer's Qualifications
Prior to installation, submit data for approval by the [_____] Division,
Naval Facilities Engineering Command, of the installer's experience and
qualifications. Show that the installer who will perform the work has a
minimum of [2] [_____] years' experience successfully installing IDS of the
same type and design as specified herein. Include names, locations, and
points of contact of at least two installations of the same type and design
as specified herein where the installer has installed such systems.
Indicate the type of each system and certify that each system has performed
satisfactorily in the manner intended for a period of not less than [12]
[_____] months
1.6.2.2
Instructor's Qualifications
Prior to installation, submit data of the instructor's experience and
SECTION 13702N