]1.4.2
Test Reports
1.4.2.1
Joint Sealant Qualification Test Reports
Submit test results from independent laboratory of representative samples
of joint sealant material. Samples must have been tested within the last
three years. Submit results as required in article entitled "Quality
Assurance Provisions" of FS TT-S-00230. Note that testing in accordance
1.4.2.2
Coatings Qualification Test Reports
Submit test results from independent laboratory of representative samples
considered to be independent laboratories for purposes of compliance with
"QUALIFICATION INSPECTION" requirements herein. Samples must have been
tested within the last three years. Submit results for epoxy materials as
required in article entitled "QUALIFICATION INSPECTION" of MIL-DTL-24441,
and as revised by article entitled "Coating System" herein. Submit results
for polyurethane materials as required in article entitled "QUALIFICATION
INSPECTION" of MIL-PRF-85285, and as revised by article entitled "Coating
System" herein. Note that requirement for "QUALIFICATION INSPECTION" is a
pre-qualification requirement, and involves the same testing required for
listing in the Qualified Products List of the respective material. See
appropriate Military Specification for specific test requirements.
1.4.2.3
Recycled Metallic Abrasive Field Test Reports (Daily and Weekly)
Submit test results from independent laboratory of daily and weekly Quality
Control testing required by SSPC AB 2.
1.4.3
Certificates
1.4.3.1
Work Plan
**************************************************************************
NOTE: For maintenance painting, add requirement for
pre-work determination of the existing surface
profile. If paint removal is specified in another
Section, such as a blast cleaning prior to
inspection or repair, or in the lead removal
Section, include this evaluation of existing profile
such that the paint removal operation does not
create excessive profile.
**************************************************************************
Submit a written plan describing in detail all phases of coating
operations. Address work sequencing, surface preparation, coating
application, recoat and cure time projections, as well as how each step
will be controlled, tested, and evaluated. [Describe process of
determining the existing surface profile under paint, and procedures for
ensuring that the profile is not increased beyond the maximum profile
specified herein. ]Describe equipment and methods used to measure and
monitor weather conditions, including but not limited to temperature,
manufacturer's instructions, for repairing defects in the coating film such
as runs, drips, sags, holidays, overspray, etc. Address safety measures,
SECTION 09971
Page 12