for damage prior to use and return non-compliant materials to manufacturer.
immediately and notify the Contracting Officer. Expired materials may be
returned to manufacturer, tested, and if compliant, issued a shelf life
extension.
1.6
COATING HAZARDS
**************************************************************************
NOTE: This specification Section should be used
with NFGS-01525 "SAFETY REQUIREMENTS".
**************************************************************************
Ensure that employees are trained in all aspects of the safety plan.
improperly handled. The coating manufacturer's written safety precautions
shall be followed throughout mixing, application, and curing of the
coatings. During all cleaning, cleanup, surface preparation, and paint
application phases, ensure that employees are protected from toxic and
Comply with respiratory protection requirements in 29 CFR 1910.134. The
1.7
JOB SITE REFERENCES
**************************************************************************
NOTE: Include any other jobsite related references
that might be added during design.
**************************************************************************
Make available to the Contracting Officer at least one copy each of ASTM D
3276, ASTM D 3925, ASTM D 4285, ASTM D 4417, SSPC SP COM, SSPC SP 1, SSPC
SP 7, SSPC SP 10, SSPC PA 1, SSPC PA 2, [SSPC Guide 6, ]SSPC Guide 12, SSPC
Guide to VIS 1, SSPC VIS 1, and an SSPC Certified Contractor Evaluation
Form at the job site.
1.8
PRE-APPLICATION MEETING
**************************************************************************
NOTE: The Coating Manufacturer's rep may be
included for unusually large or complicated projects.
**************************************************************************
After approval of submittals but prior to the initiation of coating work,
Contractor representatives, including at a minimum, project superintendent
and QC manager, paint foreman, Contracting Officer representatives, coating
inspector, [and coating systems manufacturer's representative ]shall have a
pre-application coating preparatory meeting. This meeting shall be in
addition to the pre-construction conference. Specific items addressed
shall include: work plan, safety plan, inspection standards, inspector
safety plan, and test logs. Notify Contracting Officer at least ten days
prior to meeting.
PART 2
PRODUCTS
2.1
JOINT SEALANT
TT-S-00230, Type II, Class B
SECTION 09971
Page 16