excavation.
1.3.4
Unclassified Excavation
Unclassified excavation will be paid for at the contract unit price per
cubic meter yard for unclassified excavation.
1.3.5
Classified Borrow
Classified borrow will be paid for at the contract unit prices per cubic
meter yard for common or rock borrow.
1.3.6
Unclassified Borrow
Unclassified borrow will be paid for at the contract unit price per cubic
meter yard for unclassified borrow.
1.3.7
Authorized Overhaul
The number of station-meters station-yards of overhaul to be paid for will
be the product of number of cubic meters yards of overhaul material
measured in the original position, multiplied by the overhaul distance
measured in stations of 100 meters feet and will be paid for at the
contract unit price per station-meter station-yard for overhaul in excess
of the free-haul limit as designated in paragraph DEFINITIONS.
1.3.8
Sheeting and Bracing
**************************************************************************
NOTE: Delete subparagraphs or items not required in
the project.
**************************************************************************
Sheeting and bracing, when shown or authorized by the Contracting Officer
to be left in place, will be paid for as follows: [_____].
1.3.8.1
Timber Sheeting
Timber sheeting will be paid for as the number of board feet of lumber
below finish grade measured in place prior to backfilling. Sheeting wasted
when cut off between the finished grade and 300 mm 1 foot below the
finished grade also shall be included in the measurement.
1.3.8.2
Steel Sheeting and Soldier Piles
**************************************************************************
NOTE: The blank will be filled with an appropriate
number not greater than 1 meter (3 feet). However,
if the quantities of sheeting involved are
anticipated to be substantial, and since the cut off
steel can be sold by the Contractor as scrap, the
whole part in brackets can be deleted and no payment
provided for wasted cut off ends.
**************************************************************************
Steel sheeting, soldier piles, and steel bracing will be paid for according
to the number of pounds of steel calculated. This calculation shall be
made by multiplying the measured in-place length in meters feet below
finish grade by the unit weight of the section in kg per meter pounds per
SECTION 02300
Page 10