Governement will disconnect and seal utilities.
**************************************************************************
Maintain existing utilities indicated to stay in service and protect
against damage during demolition operations. Prior to start of work,
[utilities serving each area of alteration or removal will be shut off by
the Government and disconnected and sealed by the Contractor] [the
Government will disconnect and seal utilities serving each area of
alteration or removal upon written request from the Contractor].
1.6.8
Facilities
Protect electrical and mechanical services and utilities. Where removal of
existing utilities and pavement is specified or indicated, provide approved
barricades, temporary covering of exposed areas, and temporary services or
connections for electrical and mechanical utilities. Floors, roofs, walls,
columns, pilasters, and other structural components that are designed and
constructed to stand without lateral support or shoring, and are determined
to be in stable condition, must remain standing without additional bracing,
shoring, or lateral support until demolished, unless directed otherwise by
the Contracting Officer. Ensure that no elements determined to be unstable
are left unsupported and place and secure bracing, shoring, or lateral
supports as may be required as a result of any cutting, removal, or
demolition work performed under this contract.
1.6.9
Protection of Personnel
Before, during and after the demolition work the Contractor shall
continuously evaluate the condition of the structure being demolished and
demolition site. No area, section, or component of floors, roofs, walls,
columns, pilasters, or other structural element will be allowed to be left
standing without sufficient bracing, shoring, or lateral support to prevent
collapse or failure while workmen remove debris or perform other work in
the immediate area.
1.7
BURNING
The use of burning at the project site for the disposal of refuse and
debris [will not be permitted] [will be permitted in the area located
[_____] and between the hours of [_____] and [_____]]. Where burning is
permitted, adhere to federal, state, and local regulations.
1.8
FOREIGN OBJECT DAMAGE (FOD)
**************************************************************************
NOTE: Delete requirements if inapplicable.
Some large scale apron, hangar, or other type
projects to be constructed adjacent to areas with
operational aircraft may require temporary
barricades or debris fences installed in place prior
to the start of work. The station's air operations
and public works departments must be contacted by
the designer to determine project requirements. If
fences or other type barricades are required, they
must be designed and located to suit the project
**************************************************************************
SECTION 02220