submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
As-Built Drawings
Drawings showing final as-built conditions of the project. [The
final CADD as-built drawings shall consist of one set of
electronic CADD drawing files in the specified format, one set of
mylar drawings, 2 sets of blue-line prints of the mylars, and one
set of the approved working as-built drawings.] [The manually
prepared drawings shall consist of 1 set of completed final
as-built original transparency drawings, 2 sets of blue-line
prints of the transparencies, and the approved marked working
as-built prints.]
SD-03 Product Data
As-Built Record of Equipment and Materials
[Two] [_____] copies of the record listing the as-built
materials and equipment incorporated into the construction of the
project.
Warranty Management Plan
[One set] [[_____] sets] of the warranty management plan
containing information relevant to the warranty of materials and
SECTION 01780A