that a "Final" inspection with the Client can be scheduled. Any items
noted on the "Pre-Final" inspection shall be corrected in a timely manner
and shall be accomplished before the contract completion date for the
work,or any particular increment thereof, if the project is divided into
increments by separate completion dates.
1.14.3
Final Acceptance Inspection
The Contractor shall notify the Contracting Officer at least 14 calendar
days prior to the date a final acceptance inspection can be held. The
notice shall state that all items previously identified on the pre-final
punch list will be corrected and acceptable, along with any other
unfinished Contract work, by the date of the final acceptance inspection.
The Contractor shall be represented by the QC Manager, the Project
Superintendent, and others deemed necessary. Attendees for the Government
will include the Contracting Officer, other ROICC personnel, and personnel
representing the Client. Failure of the Contractor to have all contract
work acceptably complete for this inspection will be cause for the
Contracting Officer to bill the Contractor for the Government's additional
inspection cost in accordance with the Contract Clause entitled "Inspection
of Construction."
1.15
TRAINING
Prior to acceptance of the facility by the Contracting Officer for
beneficial occupancy, the QC Manager shall provide a comprehensive
project-specific Government personnel training program for the systems of
the facility specified in the technical specifications of this Contract.
The core of this training will be based on manufacturer's recommendations
and the operation and maintenance information provided as a part of this
Contract. [The course shall provide a brief summary of Part I, "Facility
Information" and a more detailed presentation of Part II, "Primary Systems
Section 01782 FACILITY OPERATION AND MAINTENANCE SUPPORT INFORMATION. The
presentation shall be weighted so as to spend 95% of instruction time on
Part II.] Instructors shall be well-versed in the particular systems that
they are presenting. Provide instruction time on site at a location
approved by the Contracting Officer.
1.15.1
Training Outline
Provide each trainee in the course a written course outline, listing the
major and minor topics to be discussed by the instructor on each day of the
course.
1.15.2
Video Recording
Provide to the Contracting Officer two copies of the training course in
[DVD][VHS] video recording format. The recording shall capture, in video
and audio, all instructors' training presentations including question and
answer periods with the trainees.
1.15.3
Unresolved Questions From Trainees
If, at the end of the training course, there are questions from trainees
that remain unresolved, the instructor shall send the answers, in writing,
to the Contracting Officer for transmittal to the trainees, and the
training video should be modified to include the appropriate clarifications.
SECTION 01450N
Page 22