responsibilities. Provide a final copy of Sections I through V and
Section XIII from the Construction QC Plan. Highlight the [__] as the
designated Commissioning Agent.
d. A description of the management, communication, and reporting of
the Commissioning Plan.
e.
An outline of the commissioning process scope including:
(1) Submittal review procedures.
Provide a copy of Section VI of
the QC Plan.
(2) Observation procedures. Provide a copy of Sections IX, X,
XII, and XIV of the QC Plan. Highlight the requirements for
verification of the correct installation of all systems.
(3) Start-up and Testing procedures.
Provide copies of Sections
VII & VIII of the QC Plan.
(4) Training activities.
Provide a copy of Section XV of the QC
Plan.
(5) O&M Documentation. Describe the information to be provided
to the client as required by Specification Section 01782 FACILITY
OPERATION AND MAINTENANCE SUPPORT INFORMATION.
(6)
Warranty period activities.
f.
A listing of the written work products.
g.
An activity schedule.
h. A description of the rigor and scope of testing:
Provide a copy of
Section VII of the QC Plan.
1.18.2
Commissioning Agent Certification Letter
Produce a letter signed by the Contractor's Commissioning Agent certifying
the Commissioning Plan has been successfully executed and the design intent
of the facility has been achieved.
]PART 2
PRODUCTS
Not used.
PART 3
EXECUTION
Not used.
-- End of Section --