marked to show deviations which have been made from the Contract drawings.
Ensure each deviation has been identified with the appropriate modifying
documentation (e.g. PC No., Modification No., Request for Information No.,
etc.). The QC Manager [or QC Specialist assigned to an area of
responsibility ]shall initial each revision. Upon completion of work, the
QC Manager shall furnish a certificate attesting to the accuracy of the
as-built drawings prior to submission to the Contracting Officer.
1.17
NOTIFICATION ON NON-COMPLIANCE
The Contracting Officer will notify the Contractor of any detected
non-compliance with the Contract. The Contractor shall take immediate
corrective action after receipt of such notice. Such notice, when
delivered to the Contractor at the work site, shall be deemed sufficient
for the purpose of notification. If the Contractor fails or refuses to
comply promptly, the Contracting Officer may issue an order stopping all or
part of the work until satisfactory corrective action has been taken. No
part of the time lost due to such stop orders shall be made the subject of
[1.18
U. S. GREEN BUILDING COUNCIL LEED CERTIFICATION REQUIREMENTS
**************************************************************************
NOTE: For projects to be submitted for LEED
certification, include this paragraph. As a
minimum, systems to be commissioned for LEED
certification include interior and exterior lighting
systems, plumbing fixtures and infrastructure,
irrigation systems, HVAC systems, temperature and
humidity controls, monitoring controls, occupant
systems and advanced technologies. Consider
modifying the paragraph entitled "QC Specialists
Duties and Qualifications" to provide QC Specialist
to commission those systems if necessary.
**************************************************************************
This project requires LEED Certification by the U. S. Green Building
Council. The following two items are required as part of the LEED
Certification process as specified in Section 01330 SUBMITTAL PROCEDURES.
1.18.1
Commissioning Plan
Provide a copy of a Commissioning Plan, which contains the following
components:
a. A brief overview of the Commissioning Process. Briefly describe
the Quality Control and the Operation and Maintenance Support
Information (OMSI) Program requirements for the project. Provide
copies of specification Sections 01450N and 01782 FACILITY OPERATION
AND MAINTENANCE SUPPORT INFORMATION to supplement the description.
b.
Listing of all commissioned systems.
**************************************************************************
NOTE: The Project Superintendent may not be named as
**************************************************************************