1.7.2
Project Chemist
As a minimum, the Contractor's Senior Chemist shall have: a [_____] degree
in Chemistry; [_____] years of experience related to investigations,
experience in calibrating and operating various field monitoring devices;
and [_____] years of experience in the operation of an HTRW commercial
laboratory with standard analytical chemistry methods common for analyzing
soil, water, air and other materials for chemical contamination assessment,
including data for hazardous waste manifesting. The project chemist shall
ensure that all chemistry related goals of the program are attained. The
project chemist shall be onsite during all sampling events and shall also
be available for consultation with Government personnel.
1.7.3
Environmental Sampler
As a minimum, the Contractor's Environmental Sampler shall have: [a
[_____] degree in Chemistry, Environmental Science, Engineering, Geology,
Hydrology, or a related field;] [_____] years of experience in the
development and preparation of SAP and work plans; [_____] years of
experience in and knowledge of EPA methods for collecting environmental and
hazardous waste samples; [_____] years of experience in operation of field
screening equipment (e.g. PID, FID, infrared spectrometer, immunoassay,
etc.); and [_____] field seasons of experience with the particular field
screening techniques for use on this project. The Environmental Sampler
shall collect all onsite samples and perform all field screening tests.
The Environmental Sampler shall review the sampling results, and provide
recommendations for the Contractor's sampling program. The Environmental
Sampler shall be onsite during excavation and stockpiling operations
involving contaminated soil or soil to be checked for contamination.
1.8
COORDINATION MEETING
**************************************************************************
NOTE: QA of Contractor work for this contract is a
function of the Government. For CDQM, USACE has
established QA policy that is defined in ER
1110-1-263. The designer must require in the
specification that the Contractor comply with USACE
CDQM as described in ER 1110-1-263.
**************************************************************************
After the preconstruction conference, before any sampling or testing, the
Contractor and the Contracting Officer will meet at [the construction site]
[_____] to discuss the CQC Plan and the SAP. The coordination meeting will
be simultaneous to any CQC coordination meeting required in Section 01451A
CONTRACTOR QUALITY CONTROL unless otherwise indicated or directed. A list
of definable features that involve chemical measurements shall be agreed
upon. At a minimum, each matrix (soil, water, air, containerized wastes,
radioactive wastes, instrumental chemical parameter measurement, etc.)
shall be a definable work feature. Management of the chemical data quality
system including project DQO, project submittals, chemical data
documentation, chemical data assessment, required sampling and analysis
protocols, and minimum data reporting requirements shall be agreed upon.
The meeting will serve to establish an interrelationship between the
Contractor's chemical data quality management and Government chemical
by the Government and shall be signed by both the Contractor and the
Contracting Officer. The minutes will include any or all unresolved
SECTION 01450A
Page 14