3.3.2.6
Responsibility
All activities shall be identified in the project schedule by the party
responsible to perform the work. Responsibility includes, but is not
limited to, the subcontracting firm, contractor work force, or government
agency performing a given task. Activities shall not belong to more than
one responsible party. The responsible party for each activity shall be
identified by the Responsibility Code.
3.3.2.7
Work Areas
All activities shall be identified in the project schedule by the work area
in which the activity occurs. Activities shall not be allowed to cover
more than one work area. The work area of each activity shall be
identified by the Work Area Code.
3.3.2.8
Modification or Claim Number
Any activity that is added or changed by contract modification or used to
justify claimed time shall be identified by a mod or claim code that
changed the activity. Activities shall not belong to more than one
modification or claim item. The modification or claim number of each
activity shall be identified by the Mod or Claim Number. Whenever
possible, changes shall be added to the schedule by adding new activities.
Existing activities shall not normally be changed to reflect modifications.
3.3.2.9
Bid Item
All activities shall be identified in the project schedule by the Bid Item
to which the activity belongs. An activity shall not contain work in more
than one bid item. The bid item for each appropriate activity shall be
identified by the Bid Item Code.
3.3.2.10
Phase of Work
All activities shall be identified in the project schedule by the phases of
work in which the activity occurs. Activities shall not contain work in
more than one phase of work. The project phase of each activity shall be
by the unique Phase of Work Code.
3.3.2.11
Category of Work
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
All Activities shall be identified in the project schedule according to the
category of work which best describes the activity. Category of work
refers, but is not limited, to the procurement chain of activities
including such items as submittalsdesigns, design package submissions
design reviews, review conferences, permits, submittals, approvals,
procurement, fabrication, delivery, installation, start-up, and testing.
The category of work for each activity shall be identified by the Category
of Work Code.
3.3.2.12
Feature of Work
All activities shall be identified in the project schedule according to the
SECTION 01320A
Page 7