SECTION 01320A
PROJECT SCHEDULE
05/02
**************************************************************************
NOTE: This guide specification covers the
requirements for the preparation and maintenance of
the project schedule for construction projects or
design-build construction projects..
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
This guide specification includes tailoring options
for construction projects and design-build
construction projects. Selection or deselection of
a tailoring option will include or exclude that
option in the section, but editing the resulting
section to fit the project is still required.
**************************************************************************
PART 1
GENERAL
**************************************************************************
NOTE: Selection of the optional requirements in
this guide specification should be coordinated with
Construction Division to ensure that the schedule
requirements are appropriate for the complexity of
the constructability portion of the BCOE review.
See ER 415-1-11. Paragraphs may not be removed from
this specification except as noted.
SECTION 01320A