If it is desired to monitor a Contractor's schedule
by use of an in-house program, this will require use
of the Standard Data Exchange Format (SDEF). Use of
proprietary systems will not be specified. See ER
1-1-11, Appendix A.
**************************************************************************
1.1
REFERENCES
**************************************************************************
NOTE: Issue (date) of references included in
provided by the latest guide specification. Use of
SpecsIntact automated reference checking is
recommended for projects based on older guide
specifications.
**************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11
(1995) Progress, Schedules, and Network
Analysis Systems
1.2
QUALIFICATIONS
The Contractor shall designate an authorized representative who shall be
responsible for the preparation of all required project schedule reports.
PART 2
PRODUCTS (Not Applicable)
PART 3
EXECUTION
3.1
GENERAL REQUIREMENTS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
Pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS, a
Project Schedule as described below shall be prepared. The scheduling of
constructiondesign and construction shall be the responsibility of the
Contractor. Contractor management personnel shall actively participate in
its development. Subcontractors and suppliersDesigners, Subcontractors and
suppliers working on the project shall also contribute in developing and
maintaining an accurate Project Schedule. The approved Project Schedule
shall be used to measure the progress of the work, to aid in evaluating
time extensions, and to provide the basis of all progress payments.
3.2
BASIS FOR PAYMENT
The schedule shall be the basis for measuring Contractor progress. Lack of
an approved schedule or scheduling personnel will result in an inability of
the Contracting Officer to evaluate Contractor's progress for the purposes
SECTION 01320A
Page 4