of over 90 days. Examples of procurement process activities include, but
are not limited to: submittals, approvals, procurement, fabrication, and
delivery.
3.3.2.4
Critical Activities
The following activities shall be listed as separate line activities on the
Contractor's project schedule:
a. Submission and approval of mechanical/electrical layout drawings.
b. Submission and approval of O & M manuals.
c. Submission and approval of as-built drawings.
e. Submission and approval of testing and air balance (TAB).
f. Submission of TAB specialist design review report.
g. Submission and approval of fire protection specialist.
h. Submission and approval of testing and balancing of HVAC plus
i. Air and water balance dates.
k. Controls testing plan.
l. Controls testing.
m. Performance Verification testing.
n. Other systems testing, if required.
o. Prefinal inspection.
p. Correction of punchlist from prefinal inspection.
q. Final inspection.
3.3.2.5
Government Activities
**************************************************************************
NOTE: NOTE: Selection of construction or
design-build construction text required.
**************************************************************************
Government and other agency activities that could impact progress shall be
shown. These activities include, but are not limited to: approvals,
approvals, design reviews, environmental permit approvals by State
regulators, inspections, utility tie-in, Government Furnished Equipment
(GFE) and Notice to Proceed (NTP) for phasing requirements.