1.4.3
Group III Technical Data Package
**************************************************************************
NOTE: Insert section number and title for the UMCS
specification.
**************************************************************************
The Group III technical data package shall consist of factory testing data.
The Contractor shall prepare and submit test procedures using Section
[_____] as a guide for the factory test. The procedures shall explain in
detail, step-by-step actions and expected results to demonstrate compliance
with the specified requirements, and the methods for simulating the
necessary conditions of operation to demonstrate performance of the system.
The factory test shall be designed to demonstrate the operation of the
stand-alone controller and its associated software and of the UMCS
interface and the ability of the proposed system to comply with specified
requirements.
1.4.4
Group IV Technical Data Package
1.4.4.1
Performance Verification and Endurance Testing Data
**************************************************************************
NOTE: Insert section number and title for the UMCS
specification.
**************************************************************************
The Contractor shall prepare and submit test procedures using Section
[_____] as a guide, excluding all surge and overvoltage tests, for the
performance verification test and endurance test. Surge and overvoltage
tests shall not be conducted during the performance verification test. The
test procedures shall describe the applicable tests to be performed, and
other pertinent information such as specialized test equipment required,
and length of performance verification test. The test procedures shall
explain in detail, step-by-step actions and expected results to demonstrate
compliance with the specified requirements. Receiver input signal voltages
and S/N ratios as required by the RF area coverage report shall be verified
as adequate for system operation. Performance verification and endurance
test procedures shall be submitted by the Contractor and approved by the
Government in writing before starting tests.
1.4.4.2
Operation and Maintenance Data
A draft copy of the operation and maintenance data, in manual format, as
specified for the Group V technical data package, shall be delivered to the
Government prior to beginning the performance verification test, for use
during site testing.
1.4.4.3
Training Data
Lesson plans and training data, in manual format, for the training phases,
including type of training to be provided, with a list of reference
material, shall be delivered for approval.