Balanced Digital Multipoint System
EIA ANSI/TIA/EIA-606A
(2002) Administration Standard for the
Telecommunications Infrastructure
EIA TIA/EIA-455-104A
(2000) FOTP-104 Fiber Optic Cable Cyclic
Flexing Test
EIA-455-88
(2001) FOTP-88 Fiber Optic Cable Bend Test
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2
(2002) National Electrical Safety Code
IEEE C62.41
(1991; R 1995) Recommended Practice for
Surge Voltages in Low-Voltage AC Power
Circuits
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA 250
(2003) Enclosures for Electrical Equipment
(1000 Volts Maximum)
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70
(2005) National Electrical Code
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
47 CFR 15
UNDERWRITERS LABORATORIES (UL)
UL 1666
(2000; Rev thru Jul 2002) Test for Flame
Propagation Height of Electrical and
Optical-Fiber Cables Installed Vertically
in Shafts
1.2
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
SECTION 16768A
Page 7