zone lights as shown on the plan drawings.
c. Installation details shall indicate layout and mounting of equipment,
equipment relationship to other parts of the work, including clearances
required for maintenance and operation, and plan and elevation details that
indicate the exact and totally coordinated physical location and size of
each individual item of equipment.
d. Details of the custom assembly of equipment shall indicate the assembly
configuration, elevations and dimensions. Typical custom assembly details
include equipment panels, and equipment mounted in a rack or cabinet.
1.5
QUALITY ASSURANCE
1.5.1
Qualifications
1.5.1.1
General Qualification Requirements
**************************************************************************
NOTE: If the NCTV System is to be procured and
provided as part of the facility construction
contract, include paragraph "(1)" under item "e."
If the NCTV System is to be provided as part of a
separate RFP procurement of telecommunications
systems, then delete paragraph "(1)" under item "e".
**************************************************************************
a. The NCTV System Contractor, Installer and Manufacturer shall each have
the minimum qualifications specified, related to the type of system
specified for this project.
b. The Government reserves the right to accept or reject the system
Contractor, Installer or Manufacturer based upon qualifications and ability
to conform to specified requirements of this Section. System Contractors,
Installers and Manufacturers that do not have the specified qualifications
will not be acceptable and shall not be allowed to perform the work of this
Section.
c. The Government will determine the acceptability of any proposed system
Contractor, Installer and Manufacturer based on submitted and verified
documentation that substantiates that the proposed system Contractor,
Installer and Manufacturer have the qualifications specified in this
Section.
d. The project Electrical Contractor shall not procure or install the
system cabling or equipment unless said Electrical Contractor is separately
and distinctly qualified as the system Contractor and/or Installer in
accordance with the qualifications specified in this Section.
e. The system Contractor shall submit documented verification of the
specified qualifications as part of the Preconstruction qualification
submittal. The Government will have the right to request, inspect and
verify references and resumes of all technical and managerial personnel
assigned to the project. Qualification documentation shall include, but
not be limited to the information outlined below.
(1) A list of projects performed by the system Contractor and
Installer during the last five years explicitly involving the type of