c.
System startup and shutdown operations.
d.
e. A typical zone layout showing light locations, isolux
As-Built Drawings
Final as-built drawings shall be finished drawings on mylar or
vellum and shall be delivered with the final test report.
SD-03 Product Data
Equipment and Materials
Data published by the manufacturer of each item on the list of
equipment and material, to permit verification that the item
proposed is of the correct size, properly rated or applied, or is
otherwise suitable for the application and fully conforms to the
requirements specified.
Spare Parts
Spare parts data for each item of material and equipment
specified.
SD-06 Test Reports
CCTV Assessment Lighting[; G][; G, [_____]]
Test procedures and reports for CCTV assessment lighting. After
receipt by the Contractor of written approval of the test
procedures, the Contractor shall schedule the tests. The final
test procedures report shall be delivered after completion of the
tests.
Operating Test[; G][; G, [_____]]
Test procedures and reports for the Operating Test. After
receipt by the Contractor of written approval of the test
procedures, the Contractor shall schedule the tests. The final
test procedures report shall be delivered after completion of the
tests.
The measured resistance to ground of each separate grounding
installation, indicating the location of the rods, the resistance
of the soil in ohms per millimeter and the soil conditions at the
time the measurements were made. The information shall be in
writing.
SD-10 Operation and Maintenance Data
Lighting System
beginning the tests for use during site testing. Final copies of
SECTION 16528A
Page 12