NOTE: Delete module references if not needed.
**************************************************************************
With the battery fully charged, the system shall undergo a complete battery
discharge test to full depletion and a recharge to nominal conditions.
Instrument readings shall be recorded every minute during discharge for the
following:
a.
Battery voltage for each module.
b.
Battery current for each module.
c.
Output voltage (all three phases) for each module.
d.
Output current (all three phases) for each module.
e.
Output kilowatts for each module.
f.
Output voltage (all three phases - system output).
g.
Output current (all three phases - system output).
h.
Output kilowatts (system output).
i.
3.3
POSTING FRAMED DATA AND INSTRUCTIONS
Framed data and instructions containing wiring and control diagrams under
glass or in laminated plastic shall be posted where directed. Condensed
specified above and posted beside the diagrams. The framed instructions
shall be posted before acceptance testing of the system.
3.4
FIELD TRAINING
**************************************************************************
NOTE: Delete video tape references if not required.
Insert correct ratings and data for all bracketed
items in the following six data sheet pages. The
numbers within brackets are only examples and
correct values should be inserted.
**************************************************************************
A field training course shall be provided for designated operating and
maintenance staff members. Training shall be provided for a total period
of 12 hours of normal working time and shall start after the system is
functionally complete but prior to final acceptance test. Field training
The 12 hours shall be divided into two sessions of 6 hours each. Each
session shall be conducted on a different day. [Field training shall be
videotaped and the tape shall be left with the Contracting Officer.] [A
factory training videotape shall be provided as part of the training
materials.]
SECTION 16265A
Page 42