included in the contract documents.
**************************************************************************
The battery support system shall [conform to Sections 13080 SEISMIC
PROTECTION FOR MISCELLANEOUS EQUIPMENT, 15070A SEISMIC PROTECTION FOR
MECHANICAL EQUIPMENT, AND 16070A SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT] [be as indicated].
2.13.9
Battery Monitor
A battery monitor shall be provided for each battery pack assembly.
At a
minimum, this device shall monitor the following parameters:
a.
Total system voltage.
b.
Ambient room temperature.
c.
less] [greater than 30 seconds but less than 5 minutes] [greater
than 5 minutes].
The monitor shall also record the total accumulated discharge minutes and
accumulated battery system discharge kW hours.
2.14
FACTORY TESTING
**************************************************************************
NOTE: Edit as required for single module system.
The designer should carefully evaluate the UPS
application and the user's mission to determine
critical tests for the UPS that will ensure UPS/load
compatibility. These tests should be conducted at
the factory and the results validated prior to
shipment to the site. The required UPS/load
interaction can be achieved by requesting the
deems necessary:
a. Tests to ensure that the UPS rated power factor
is verified;
b. Tests to ensure that the UPS system will operate
in total accord and support the rated load;
c. Tests to ensure that the UPS system can deal
with load anomalies (odd harmonics, etc.) associated
with the user's equipment load.
**************************************************************************
The UPS system shall be factory tested to meet the requirements specified
using a test battery (not the battery to be supplied with the system). UPS
module shall be factory load tested as an independent assembly with 3-phase
ac input power and with battery power for a minimum of 8 hours, with meter
readings taken every 30 minutes. Load shall be balanced at rated kVA and
rated power factor. Factory tests for the UPS module shall be run under
full load, and will be witnessed by the Government. Should a malfunction
occur, the problem shall be corrected and the test shall be repeated. As a
minimum, the factory tests shall include the parameters described in
SECTION 16265A