c. [Six] [_____] copies of the Factory Test data described
below in 215.9 x 279.4 mm (8-1/2 x 11 inch) 8-1/2 x 11 inch
binders having a minimum of 3 rings from which material may
readily be removed and replaced, including a separate section for
each test. Sections shall be separated by heavy plastic dividers
with tabs. Data plots shall be full size (215.9 x 279.4 mm (8-1/2
x 11 inch) 8-1/2 x 11 inch minimum), showing grid lines, with full
resolution.
(1)
A detailed description of the procedures for factory
tests.
(2)
A list of equipment used, with calibration certifications.
(3)
A copy of measurements taken, with required plots and
graphs.
(4)
The date of testing.
(5)
A list of the parameters verified.
(6)
The condition specified for the parameter.
(7)
The test results, signed and dated.
(8)
A description of adjustments made.
Onsite Inspection and Tests[; G][; G, [_____]]
a. A letter giving notice of the proposed dates of onsite
inspections and tests at least [14] [_____] days prior to
beginning tests.
b. A detailed description of the Contractor's procedures for
onsite tests including the test plan and a listing of equipment
necessary to perform the tests. Submission shall be at least
[_____] days prior to beginning tests.
c. [Six] [_____] copies of the onsite test data described below
in 215.9 x 279.4 mm (8-1/2 x 11 inch) 8-1/2 x 11 inch binders
having a minimum of 3 rings from which material may readily be
removed and replaced, including a separate section for each test.
Sections shall be separated by heavy plastic dividers with tabs.
Data plots shall be full size (215.9 x 279.4 mm (8-1/2 x 11 inch)
8-1/2 x 11 inchminimum), showing grid lines, with full resolution.
(1)
A detailed description of the procedures for onsite tests.
(2)
A list of equipment used, with calibration certifications.
(3)
A copy of measurements taken, with required plots and
graphs.
(4)
The date of testing.
(5)
A list of the parameters verified.
(6)
The condition specified for the parameter.