program will be able to operate and maintain the flue gas cleaning system
for the Government. Furthermore, the training manuals and testing
materials shall provide information so that, in conjunction with the
training of new operators can be accomplished without the assistance of the
Contractor.
1.10.1
Training Manuals
Provide training manuals covering the complete FGD system and including
separate sections devoted to each major equipment item including spray
dryer sulfur dioxide absorbers, fabric filter baghouses, lime system,
induced draft fans, and system control panel. Each section shall include
hardware, and relation to other equipment. Furnish [_____] copies and an
original of the complete training manual.
1.10.2
Testing Program
Furnish a written testing program designed to objectively determine the
individual level of comprehension of the material presented in the training
program to the participants. Use the testing program in conjunction with
the classroom instruction. Provide [_____] copies of the complete testing
program.
1.10.3
Classroom Instruction
Develop and present 40-hour course of organized classroom instruction by
experienced engineers. The classroom instruction shall cover theory and
provided in the training manuals. Administrate the testing program at the
conclusion of the course. Present the course at least twice in order to
accommodate Government operating personnel. The Contractor shall arrange
with the Contracting Officer for classroom space and times for the classes
to be given.
1.10.4
Field Instructions
Service engineer shall provide 8-hour per day supervision of the system for
a period of 30 days after start-up to assist and instruct Government's
operations. Instruction shall include, but not be limited to the following:
a.
Actual start-up and shutdown of the FGD system for each boiler.
b.
Indoctrination to the lime handling system, stressing safety.
c.
Remove and install one atomizer.
d.
Disassemble and assemble one atomizer to the extent required for
normal maintenance.
e.
Review of instrument, gage, and control functions in the control
room.
f.
Deliberate upset of FGD system and instruction on making necessary
corrections.
g.
Simulation of induced fan failure.
SECTION 15864N