h.
Review of fabric filter baghouse maintenance including removal and
replacement of bags.
1.10.5
Video Recording
Furnish color video tapes made during field instruction or prepared color
video tapes covering the field instruction material. Video tapes
instruction and hands-on-training, along with prepared video instruction
tapes, shall become the property of the Government.
1.11
MODEL DELIVERY
The model shall remain the property of the Government, and shall be
delivered to the Government upon request by the Contracting Officer within
one year of start-up. The model shall include a support table as part of
the deliverable items.
1.12
POSTED OPERATING INSTRUCTIONS
Provide for the following:
a.
Atomizers
b.
Lime feeders
c.
Baghouse
d.
Lime slakers
e.
Lime unloading
PART 2
PRODUCTS
2.1
APPLICATION
**************************************************************************
NOTE: Refer to ICAC FGD1 for additional flue gas
desulfurzation terminology.
**************************************************************************
The Flue Gas Cleaning System and induced draft fans shall be used to
control emissions of sulfur dioxide and particulate matter and furnace
draft from steam generators. The steam generators will be
[stoker][pulverized] coal-fired and will also be capable of 100 percent oil
firing. Boilout and start-up of the boilers will be with No. [_____] fuel
oil. The steam generators will be used to supply steam to [a steam
distribution system serving process and space heating loads][a
congeneration system]. Consequently, the units will operate with a wide
load range and with rapid load changes. The maximum steam demand can be
met by operation of [_____] steam generators. A steam generator will be
available for emergency or standby service. A separate FGD system for each
steam generator as indicated. Also, provide facilities for reagent
storage, preparation, and feed. The system shall be designed to use lime
as the alkali material.
2.2
EQUIPMENT AND MATERIALS PROVIDED UNDER THIS CONTRACT
**************************************************************************
NOTE: It is not the intent of this specification to
SECTION 15864N
Page 26