percent; and net gas to cloth ratio, m/s fpm.
f.
Type of [incinerator] [coal fire boiler] at each installation.
1.2.5.2
Factory Test Completion Certification
Submit certificate of completion for factory tests on control circuits,
mechanical draft equipment, materials, and dampers except poppet dampers,
as required in paragraph entitled "Source Quality Control."
1.2.5.3
Baghouse Installation
Submit certification from the field representative that the baghouse has
been installed as recommended by the manufacturer.
1.2.6
Smoke Test
Prior to installing insulation, perform smoke tests on installed baghouse
[including pulse jet weather enclosure] to identify leaks. Use forced
draft fan to pressurize baghouse. Notify Contracting Officer or designated
Government representative of test date in writing not less than 15 working
days prior test so that Contracting Officer or designated Government
representative may witness test. Repair leaks before installing insulation.
1.2.7
Particulate Emissions Test
**************************************************************************
NOTE:
1. Emissions must comply with local, state, and
federal standards for particulate and visible
emissions. Note that compliance with particulate
emission standards does not guarantee compliance
with opacity standards; nor does compliance with
federal or state standards guarantee compliance with
local standards.
2. Opacity is influenced by particulate size
distribution. For example, approximately 25 percent
of the emissions from stoker fired boilers are below
10 microns, thus a visually acceptable stack may
result in a particulate emissions loading of 0.09s
g/m3 0.04 grains per cu ft. However, approximately
45 percent of the emissions from pulverized coal
fired boilers are below 10 microns, thus a visually
acceptable stack may result in an emissions loading
of 0.046 g/m2 0.02 grains per cu ft.
**************************************************************************
Prior to baghouse acceptance, provide simultaneous particulate emissions
tests at the baghouse inlet and at the baghouse outlet. Test to ensure
particulate emissions loadings does not exceed [_____] gram per dry std
cubic meter grains per dry std cu ft when operating at maximum continuous
flow rating and to ensure accuracy of inlet grain loading estimate.
Perform three tests using procedures and equipment as in 40 CFR 60, EPA
AP-42, Appendix A and local regulations. Operate the system in automatic
without system failure or tripout, for 30 days prior to performing tests.
Notify Contracting Officer or designated Government representative of test
date in writing not less than 15 working days prior test so that
SECTION 15863N
Page 10