Bag tests
Baghouse controls tests
Particulate emissions tests
Damper tests
Baghouse inspection
SD-07 Certificates
Certificate of experience
Particulate emissions test procedures
Factory test completion certification
Baghouse installation
SD-10 Operation and Maintenance Data
Baghouse, Data Package 3
Bypass system, Data Package 3
Dampers, Data Package 2
Fans, Data Package 3
Valves, Data Package 2
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA. Include procedures for:
a. Bag precoating.
b. Baghouse startup; initial and routine.
c. Baghouse shutdown; short duration, long duration, and
emergencies.
1.4
DELIVERY AND STORAGE
Ship equipment as shop welded, factory assembled modules, except when
physical size, arrangement, equipment configuration, or shipping
limitations, make the shipment of assembled equipment impracticable. Do
not ship modules with bags installed. Package bags separately to prevent
site. Handle, store, and protect equipment and materials to prevent damage
SECTION 15863N
Page 12