procedure, interior and exterior, for applicable items shall be
provided.
MSDS for materials provided.
specified.
Welding[; G][; G, [_____]]
A copy of qualified procedures and a list of names and
This information regarding welds internal to packaged boilers
shall be furnished if requested by the Government.
Water Treatment Plan
Plan for water treatment, including proposed chemicals to be
used and nationally recognized testing codes applicable to the
system, prior to system startup.
Cleaning of Boiler and Piping.
Procedure for cleaning, prior to connecting tubing and piping to
instruments and prior to pressure testing, test equipment use, and
cleaning after completion of testing and installation.
A detailed manufacturer's acceptance testing plan, for approval,
pressure testing and repair of piping and tubing materials failing
pressure tests.
Spare Parts
Spare parts data for each item of equipment specified.
Framed Instructions[; G][; G, [_____]]
Framed instructions containing wiring and control diagrams under
glass or in laminated plastic, to be posted where directed.
framed as specified above and posted beside the diagrams. The
framed instructions shall be posted before acceptance testing of
the systems.
SD-06 Test Reports
Test Schedule
A written schedule, [7] [_____] days before tests are performed.
Schedule will be approved by the Contracting Officer.
Proposed Test Procedure
SECTION 15561A
Page 15