The signs shall be rigidly affixed to the equipment or devices without
impairing functions or, if this is not possible, shall be attached as a tag
using a wire or chain. In addition to the identification signs, each major
component of equipment shall have a nameplate listing the manufacturer's
name, model number, and when applicable, electrical rating and other
3.2
FIELD QUALITY CONTROL
Performance of tests and inspections as specified herein to demonstrate
contract requirements. During boiler system start-up tests,
factory-trained engineers or technicians employed by manufacturer of such
components as the burner, flame safeguard and combustion controls,
present, as required, to ensure the proper functioning, adjustment, and
testing of individual components and systems, and to train plant operation
personnel in the operation and maintenance of them. No bypassing, use of
specified elsewhere. Labor, equipment, fuel, and test apparatus required
for testing shall be furnished by the Contractor.
3.2.1
Inspections and Test
Inspections and tests at the site shall be made under the direction of and
be subject to the approval of the Contracting Officer. The Contractor
shall operate [the] [each] boiler and appurtenances prior to final testing
and shall ensure that necessary adjustments have been made. A [24-] [48-]
[_____] hour advance written notice shall be submitted to the Contracting
Officer indicating the equipment is ready for testing. Provide testing
equipment, including gages, thermometers, calorimeter, CO, O2, CO2 test
equipment that independently analyzes each gas, thermocouple pyrometers,
fuel flow meters, water meters, and other test apparatus and set up and
calibrated prior to the test. Draft, fuel pressure, and steam flow may be
measured by permanent gages and meters installed under the contract. [Gas
flow may be measured by utility company meters.] Provide an analysis of
the fuel being used for tests. Control of noise levels developed by
exhaust steam, including muffler, globe, and gate valves, shall be
conducted in such a manner as not to create a nuisance or hazard, and shall
be subject to the approval of the Contracting Officer. Tests shall include
the following, and shall be performed when feasible, in the sequence listed:
a.
Strength and tightness tests - Hydro test per NAVFAC MO 324.
b.
Standards compliance tests - All environmental compliance test as
required by federal, state and local laws
c.
d.
e.
Capacity and efficiency tests per ASME PTC 4.1
f.
g.
Tests of auxiliary equipment