by showing actual location in equipment, and schematically, by
showing all interconnected or interlocked relationships between
components.
e. Foundation drawings, bolt-setting information, and
foundation bolts prior to concrete foundation construction for all
equipment indicated or required to have concrete foundations.
f. Details, if piping and equipment are to be supported other
than as indicated, which include loading and type of frames,
brackets, stanchions, or other supports.
1.6.3
Spare Parts
The Contractor shall submit spare parts data for each different item of
not later than [_____] months prior to the date of beneficial occupancy.
The data shall include a complete list of parts and supplies, with source
of supply.
PART 2
PRODUCTS
2.1
STANDARD PRODUCTS
**************************************************************************
types: dry desiccant on a rotor with hot air
regeneration and liquid desiccant with spray coils
and heated desiccant.
A schematic drawing, sequence of operation, and an
equipment schedule must be included on the drawings.
Equipment which the basic dehumidification system
vendor lists as optional or "provided by others"
must be clearly shown and sized.
**************************************************************************
Materials and equipment shall be the standard products of a manufacturer
regularly engaged in the manufacturing of such products and shall
essentially duplicate equipment which is similar in material, design, and
workmanship. The standard products shall have been in satisfactory
commercial or industrial use for two years prior to bid opening. The
two-year use shall include applications of equipment and materials under
similar circumstances and of similar size. The two years experience shall
be satisfactorily completed by a product which has been sold or is offered
for sale on the commercial market through advertisements, manufacturer's
catalogs, or brochures. Products having less than a two-year field service
record will be acceptable if a certified record of satisfactory field
operation, for not less than 6000 hours exclusive of the manufacturer's
factory tests, can be shown. All products shall be supported by a service
organization. The Contractor shall submit a certified list of qualified,
permanent service organizations for support of the equipment including
their addresses and qualifications. These service organizations shall be
reasonably convenient to the equipment installation and shall be able to
render satisfactory service to the equipment on a regular and emergency
basis during the warranty period of the contract. The system shall be a
complete stand alone system with all necessary controls, motors, fans,