in accordance with ASSE 6030.
SD-10 Operation and Maintenance Data
Plumbing System[; G][; G, [_____]]
[Six] [_____] copies of the operation manual outlining the
step-by-step procedures required for system startup, operation and
shutdown. The manual shall include the manufacturer's name, model
number, service manual, parts list, and brief description of all
equipment and their basic operating features. [Six] [_____]
copies of the maintenance manual listing routine maintenance
procedures, possible breakdowns and repairs. The manual shall
include piping and equipment layout and simplified wiring and
control diagrams of the system as installed.
1.3
GENERAL REQUIREMENTS
1.3.1
Standard Products
Specified materials and equipment shall be standard items of a manufacturer
regularly engaged in the manufacture of such products. Specified equipment
shall essentially duplicate equipment that has performed satisfactorily at
least 2 years prior to bid opening.
1.3.2
Performance Requirements
1.3.2.1
Welding
**************************************************************************
NOTE: The designer will indicate welding
delete the second bracketed statement. If the need
exists for more stringent requirements for
weldments, delete the first bracketed statement and
the welding submittal.
**************************************************************************
[Piping shall be welded in accordance with qualified procedures using
performance-qualified welders and welding operators. Procedures and
welders shall be qualified in accordance with ASME BPVC SEC IX. Welding
procedures qualified by others, and welders and welding operators qualified
by another employer, may be accepted as permitted by ASME B31.1. The
Contracting Officer shall be notified 24 hours in advance of tests, and the
tests shall be performed at the work site if practicable. Welders or
welding operators shall apply their assigned symbols near each weld they
make as a permanent record. Structural members shall be welded in
accordance with Section 05090A WELDING, STRUCTURAL.] [Welding and
nondestructive testing procedures are specified in Section 05093 WELDING
PRESSURE PIPING.]
1.3.2.2
Cathodic Protection and Pipe Joint Bonding
Cathodic protection and pipe joint bonding systems shall be in accordance
with [Section 13110A CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)] [and]
[Section 13112A CATHODIC PROTECTION SYSTEM (IMPRESSED CURRENT)].
SECTION 15405A