1.7.3
Layout and Shop Drawings
The Contractor shall submit layout and shop drawings including the
following:
a. Base-mounted equipment, complete with base and all
attachments including anchor bolt template and recommended
clearances for maintenance and operation.
b.
Complete starting system.
c.
d.
e.
f. Layout of relays, breakers, switches, and instrumentation
written description of the sequence of operation.
g. Lubrication system complete including piping, pump(s),
cooling], [electric heater], controls, and wiring.
h. Location, type, and description of vibration isolation
devices for all applications.
i. The safety system, together with a detailed description of
its operation. Wiring schematics, safety devices with a listing
of their normal ranges, alarm and shutdown valves (to include
operation parameters such as pressures, temperatures, voltages,
currents, and speeds) shall be included.
j.
Layout of the engine control panel and alarm panel.
k. Mounting and support for each panel and major piece of
electrical equipment.
l.
Engine lifting points and rigging instructions.
m. Alignment information for the engine, [gear box] and [pump]
specifying sequences, tolerances, and temperature change effects.
1.8
MAINTENANCE
1.8.1
Spare Parts for Maintenance
**************************************************************************
NOTE: Spare parts to be furnished under this
contract should be specified here. The designer is
responsible for determining and providing a list of
spare parts requirements. The following is a
partial list:
**************************************************************************
The following minimum spare parts shall be furnished when applicable to the
type of engine proposed.
SECTION 15133A