bound separately of the Operation and maintenance manual with a
flexible, durable cover. Drawings incorporated in the parts lists
may be reduced to page size provided they are clear and legible,
or they may be folded into the bound lists to page size.
Photographs or catalog cuts of components may be included for
identification.
Submit sufficient hydraulic computations to substantiate pump
selection and demonstrate that the selected pump can meet the
project design and operating requirements as specified.
Installation Instruction Manual[; G][; G, [_____]]
No later than 30 days prior to time of pump delivery, submit
three copies of a typed and bound manual describing procedures to
be followed by the installation engineer in assembling,
installing, and dry- and/or wet-testing the pump. Coordinate and
consolidate the description of the pump with similar descriptions
for other specified pump parts. The description shall be of such
a nature that it may be comprehended by an engineer or mechanic
without extensive experience in erecting or installing pumps of
this type. The description shall be a step-by-step explanation of
operations required, and shall include, where applicable, such
things as alignment procedures, bolt torque values, recommended
instrument setups, recommended gauges and instruments, and similar
details.
Factory Test
Submit a description of the factory test setup and test
procedure proposed. Submit data and drawings sufficient to
demonstrate that testing is in compliance with HI 2.6.
Pump Field Tests[; G][; G, [_____]]
Submit the field test plan prior to field testing.
SD-06 Test Reports
Factory Test Report[; G][; G, [_____]]
Within 30 days of receipt of approval of the witnessed field
test, submit nine bound copies of a report covering test setup and
performance tests. The factory test report shall include the
specified information.
Field Test Report[; G][; G, [_____]]
Submit five (5) copies of the field test report.
Installation and Start-Up Engineer
Submit the installation report.
SD-10 Operation and Maintenance Data
Operating and Maintenance Instructions[; G][; G, [_____]]