followed by erecting engineer in erecting, assembling, installing,
and dry-and wet-testing pump. To the extent necessary or
desirable, coordinate and consolidate description of pump with
similar descriptions specified for [gear reducer and diesel
engine] [motor] [gear reducer].
Description shall be complete, orderly, step-by-step explanation
of operations required, and shall also include such things as
alignment procedures, bolt torque values, permissible blade/bowl
clearances; permissible bowl out-of-roundness; permissible shaft
misalignment; recommended instrument setups; recommended gages and
instruments; bearing clearances; and similar details.
Description shall be complemented and supplemented by drawings,
sketches, photos, and similar materials to whatever extent
necessary or desirable, and the overall result shall be a
description that may be comprehended by an engineer or mechanic
without extensive experience in erecting or installing pumps of
this type.
Field Tests
**************************************************************************
NOTE: Select appropriate alternate paragraph.
**************************************************************************
[Prior to proceeding with construction of the test setup but not
later than [60] [90] days after date of notice to proceed, submit
a description of the test setup and test procedure proposed.
Include dimensioned drawings and cross-sectional views of the
setup and pump, respectively, with location of instruments and
points of their connection shown.]
[Prior to proceeding with the construction of the model, but not
later than 90 days after the date of notice to proceed, submit a
description of the proposed model and test procedure. Included
therein shall be dimensioned drawings and cross-sectional views of
the model pump showing with the location of all instruments and
the point of their connection to the model.]
SD-04 Samples
Materials[; G][; G, [_____]]
Submit samples of materials as directed. Equipment, materials,
and articles installed or used without the approval of the
Contracting Officer shall be at risk of subsequent rejection.
SD-06 Test Reports
Witness Test[; G][; G, [_____]].
Submit notification that the witness test is ready to be run
along with curves and sample calculations required by paragraph
WITNESS TEST.
Factory Test[; G][; G, [_____]]
Submit a factory test report as required by paragraph TEST