Field Testing
Submit procedures for field testing as specified in paragraph
FIELD TESTING. Submit his proposed testing program at least 4
weeks prior to the first scheduled test to ensure agreement as to
personnel required and scope of the testing program.
SD-06 Test Reports
Shop Tests
Field Tests
Submit operational test reports for all required shop testing
and testing of the equipment after installation.
[Piston Rods (Standard Design)]
[Piston Rods (Corps Design)]
Submit certified test report of the corrosion resistant test on
ceramic coating as specified in paragraph(s) [PISTON RODS
(STANDARD DESIGN)] [PISTON RODS (CORPS DESIGN)].
SD-10 Operation and Maintenance Data
Operation and Maintenance
Submit operation and maintenance requirement as specified.
1.4
PRODUCTS INSTALLED BUT NOT FURNISHED
**************************************************************************
NOTE: List all property which will be furnished to
the Contractor for installation. Materials and
equipment which are purchased by supply contract by
the Government to be furnished to the Contractor
must be deleted from other portions of this
specification.
**************************************************************************
Pursuant to Contract Clause GOVERNMENT-FURNISHED PROPERTY (SHORT FORM), the
Government will furnish to the Contractor the following property if
required, to be incorporated or installed in the work. Such property will
be furnished at the project site and the Contractor shall accept delivery.
All such property shall be installed or incorporated into the work at the
expense of the Contractor. The Contractor shall verify the quantity and
condition of such Government-furnished property when delivered to him,
acknowledge receipt thereof in writing and in case of damage to or shortage
of such property, shall within 24 hours report in writing such damage or
shortage.
1.5
SYSTEM DESCRIPTION
The work covered by this section of the specifications consists of detailed
requirements for the [design,] fabrication, shop assembly, testing,
the [intake gates] [slide gates] [control gates] [tainter gates] [miter
shown.
SECTION 15010A
Page 10