Crane track material, especially fittings,
frequently require long lead time to become
available to the Contractor. Ensure that the lead
time required for material specified in this guide
specification is considered when project
construction time is established.
**************************************************************************
**************************************************************************
NOTE: TO DOWNLOAD UFGS GRAPHICS
Go to http://www.ccb.org/docs/ufgshome/graphtoc.pdf.
**************************************************************************
**************************************************************************
NOTE: The following information shall be shown on
1.
Existing material to be reused, if required
2.
Crane rail system type
3.
Crane wheel type
4.
5.
Switch throw mechanism
6. Utility line connections for power operated
switch throw mechanism
7. Drainage for track fittings and switch throw
mechanism housings
8.
Rail alignment and gage
9.
Rail joint connection types
10.
Welding method at each welded joint
11.
Sketch No. 14606-1 and Sketch No. 14606-2
Scheduling restraints which impact on the
Contractor's time or cost to perform the work,
station operations affected by the Contractor's
work, and station operations which may affect the
performance of the Contractor's work and should be
addressed in Section 01310, "Administrative
Requirements." The following is a sample paragraph
which may be used in Section 01310, "Administrative
Requirements," paragraph "Special Scheduling
Requirements."
INTERFACE WITH TRACK OPERATIONS: Schedule work to
vehicular traffic operations. Crane and/or train
operations will be scheduled to minimize
interruptions to Contractor's work. However,
critical materials must be transported as necessary.
SECTION 14606N