d.
[1] [_____] manual stations
e.
[9] [_____] spare reams of paper for the system printer, plus
sufficient paper for fire alarm acceptance tests
f.
[2] [_____] smoke sensors and base of each type installed
g.
h.
[3] [_____] spare printer ribbons
i.
[3] [_____] test magnets/devices for each type of sensors installed
j.
[3] [_____] break rods for manual stations
1.8.3
Parts List
Furnish a list, in duplicate, of all other parts and accessories which the
manufacturer of the system recommends to be stocked for maintenance.
1.9
KEYS
Keys and locks for equipment shall be identical. Provide not less than six
keys of each type required. Keys shall be CAT [60] [_____].
PART 2
PRODUCTS
[2.1
EXISTING FIRE ALARM EQUIPMENT
Existing fire alarm equipment shall be maintained fully operational until
the new equipment has been tested and accepted by the Contracting Officer.
As new equipment is installed, it shall be labeled "NOT IN SERVICE" until
the new equipment is accepted. Once the new system is completed, tested,
and accepted by the Government, it shall be placed in service and connected
to the station fire alarm system. New equipment shall have tags removed
and the existing equipment shall be tagged "NOT IN SERVICE" until removed
from the building.
[2.1.1
Equipment Removal
**************************************************************************
NOTE: Contact the Contracting Officer, Base Fire
Prevention Office, and/or Base Maintenance Personnel
to determine what action is appropriate for the
salvaging of existing fire alarm equipment.
**************************************************************************
After acceptance of the new system by the Contracting Officer, existing
equipment not connected to the new system shall be removed, unused exposed
conduit shall be removed, and damaged surfaces shall be restored. The
material shall be removed from the site and disposed of by the Contractor.
][2.1.2
Repair Service/Replacement Parts
Repair services and replacement parts for the system shall be furnished
under this contract and be available for a period of 10 years after the
date of final acceptance of this work by the Contracting Officer. On-site
service during the guarantee period shall be provided within 24 hours after
SECTION 13855N
Page 12