projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
The fire protection engineer, [[_____] Division][Engineering Field Activity
[____]], Naval Facilities Engineering Command will review and approve all
submittals in this section requiring Government approval.
**************************************************************************
NOTE: For projects administered by PACNAVFACENGCOM,
use the submittal paragraph below in lieu of the
above paragraph. Delete the "G" in the asterisk
tokens after each submittal item, except under
"SD-08, Statements."
**************************************************************************
[The Pacific Division, Naval Facilities Engineering Command delegates the
authority for review and approval of all submittals required by this
section to the U.S. Registered Fire Protection Engineer employed in the
quality control (QC) organization, specified under Section 01450N DESIGN
AND CONSTRUCTION QUALITY CONTROL. Submit to the Pacific Division, Naval
Facilities Engineering Command, Fire Protection Engineer two sets of
approved submittals and drawings immediately after approval but no later
than 15 working days prior to final inspection.]
SD-02 Shop Drawings
SD-03 Product Data
Digital alarm communicator receiver (DACR); G
Wiring; G
For digital alarm communicator transmitters, submit data for
each configuration required by this section.
SD-05 Design Data
SECTION 13854N
Page 7