manufacturer's name, model number, service manual, parts list, and
brief description of all equipment and their basic operating
features. [Six] [_____] copies of maintenance manual, listing
routine maintenance procedures, recommendation for maintenance
testing, possible breakdowns and repairs, and troubleshooting
guides. The manuals shall include single-line diagrams for the
system as installed; instructions in making pipe-to-reference cell
and tank-to-reference cell potential measurements and frequency of
monitoring; instructions for dielectric connections, interference
and sacrificial anode bonds; instructions shall include
precautions to ensure safe conditions during repair of pipe or
other metallic systems. The instructions shall be neatly bound
between permanent covers and titled "Operating and Maintenance
Instructions." These instructions shall be submitted for the
Contracting Officer's approval. The instructions shall include
the following:
a.
As-built drawings, to scale of the entire system,
showing the locations of the piping, location of all anodes and
test stations, locations of all insulating joints, and
structure-to-reference cell potentials as measured during the
tests required by Paragraph: TESTS AND MEASUREMENTS, of this
section.
b.
instructions in making pipe-to-reference cell potential
c.
nameplate data shall be in English.
d.
Instructions shall include precautions to insure safe
conditions during repair of pipe system.
Training Course
The proposed Training Course Curriculum (including topics and
dates of discussion) indicating that all of the items contained in
the operating and maintenance instructions, as well as
demonstrations of routine maintenance operations, including
testing procedures included in the maintenance instructions, are
to be covered.
1.3
GENERAL REQUIREMENTS
The Contractor shall furnish and install a complete, operating, sacrificial
anode cathodic protection system in complete compliance with NFPA 70, with
all applicable Federal, State, and local regulations and with minimum
requirements of this contract. In addition to the minimum requirements of
these specifications, [construction of gas pipelines and associated
cathodic protection systems shall be in compliance with 49 CFR 192] [and]
[construction of hazardous liquid pipelines, including fuel pipelines, and
associated cathodic protection systems shall be in compliance with 49 CFR
195] [and] [construction and installation of underground fuel storage tanks
and associated cathodic protection system shall be in compliance with 40
CFR 280]. The services required include planning, installation, adjusting
and testing of a cathodic protection system, using sacrificial anodes for
cathodic protection of the [Water] [Fire Protection] [Force Main] [Gas]
[_____] lines, their connectors and [lines under the slab or floor