SD-06 Test Reports
Tests and Measurements[; G][; G, [_____]]
Test reports in booklet form tabulating all field tests and
measurements performed, upon completion and testing of the
installed system and including close interval potential survey,
protection, insulated joint and bond tests, and holiday coating
test. A certified test report showing that the connecting method
has passed a 120-day laboratory test without failure at the place
of connection, wherein the anode is subjected to maximum
recommended current output while immersed in a three percent
sodium chloride solution.
Contractor's Modifications[; G][; G, [_____]]
Final report regarding Contractor's modifications. The report
shall include pipe-to-soil measurements throughout the affected
area, indicating that the modifications improved the overall
conditions, and current measurements for anodes. The following
special materials and information are required: taping materials
and conductors; zinc grounding cell, installation and testing
procedures, and equipment; coating material; system design
calculations for anode number, life, and parameters to achieve
protective potential; backfill shield material and installation
details showing waterproofing; bonding and waterproofing details;
insulated resistance wire; exothermic weld equipment and material.
SD-07 Certificates
Cathodic Protection System
Proof that the materials and equipment furnished under this
section conform to the specified requirements contained in the
referenced standards or publications. The label or listing by the
specified agency will be acceptable evidence of such compliance.
Services of "Corrosion Expert"[; G][; G, [_____]]
Evidence of qualifications of the "corrosion expert."
a.
The "corrosion expert's" name and qualifications shall
be certified in writing to the Contracting Officer prior to the
start of construction.
b.
Certification shall be submitted giving the name of the
firm, the number of years of experience, and a list of not less
than five (5) of the firm's installations three (3) or more years
old that have been tested and found satisfactory.
SD-10 Operation and Maintenance Data
Cathodic Protection System
Before final acceptance of the cathodic protection system, [six]
[_____] copies of operating manuals outlining the step-by-step
procedures required for system startup, operation, adjustment of
current flow, and shutdown. The manuals shall include the