considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Drawings[; G][; G, [_____]]
list of equipment and material including manufacturer's
descriptive and technical literature, catalog cuts, results of
maximum recommended anode current output density and the rate of
gaseous production if any at that current density. Detail
any other details required to demonstrate that the system has been
coordinated and will function properly as a unit.
Contractor's Modifications[; G][; G, [_____]]
in location, scope of performance indicating any variations from,
additions to, or clarifications of contract drawings. The
drawings shall show proposed changes in anode arrangement, anode
size and number, anode materials and layout details, conduit size,
electrically-isolating each pipe, and any other pertinent
information to proper installation and performance of the system.
SD-03 Product Data
Equipment[; G][; G, [_____]]
Within [30] [_____] days after receipt of notice to proceed, an
itemized list of equipment and materials including item number,
quantity, and manufacturer of each item. The list shall be
accompanied by a description of procedures for each type of
testing and adjustments, including testing of coating for
thickness and holidays. Installation of materials and equipment
shall not commence until this submittal is approved.
Spare Parts
Spare parts data for each different item of material and
equipment specified, after approval of detail drawings and not
later than six (6) months prior to the date of beneficial
occupancy. The data shall include a complete list of parts,
special tools, and supplies, with current unit prices and source
of supply. One (1) spare anode of each type shall be furnished.
SECTION 13110A