SD-07 Certificates
Performance test plan
Qualifications of shielding enclosure testing agency
Qualifications of installation supervision personnel
Components of shielded enclosure individually and as a system,
SD-08 Manufacturer's Instructions
Radio frequency shielded enclosure
SD-10 Operation and Maintenance Data
Radio frequency shielded enclosure, Data Package 2; G
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA. Indicate allowable loads on top of room and on
shelves mounted on walls, including permissible weights of
equipment that can be mounted on walls. Include prescribed method
of welding panels, cleaning of seams and contact fingers, bonding
jumpers, installing metallic items penetrating the shielding
material without decreasing the attenuation characteristics.
SD-11 Closeout Submittals
Radio frequency shielded enclosure record drawings
1.4
Reliability to maintain high shielding effectiveness for long term usage
with minimum maintenance shall be stressed throughout the design,
construction, and erection of the specified shielded enclosure. Particular
attention shall be paid to the total project so that corrosion and the
installation of electrical service, power line filters, ventilation and
connector panels do not derate the required shielding effectiveness. The
enclosures will be subject to varying moveable live floor loads and
continuous use of the ventilation system and ac power line filters.
1.5
DELIVERY AND STORAGE
Deliver materials to the job site in undamaged condition. Store material
to ensure proper alignment, and protect material against dampness and
accumulated moisture before and after delivery. Store materials under
cover in a well-ventilated enclosure, and do not allow materials to be
exposed to extreme changes in temperature and humidity. Do not store
materials in the building until concrete and masonry are dry.
SECTION 13094N
Page 9