Power consumption
[_____] kW/L
[Catalyst usage]
[_____] mg/L
1.4.3
Treatability Testing
**************************************************************************
NOTE: This paragraph should be deleted if previous
treatability studies have not been conducted. The
system parameters used during the treatability study
may not duplicate the system proposed by the
Contractor. The previous treatability studies
should be properly documented to include the
information contained in ETL 1110-1-161.
**************************************************************************
The previously conducted treatability study information contained in
Appendix [_____] is provided for the Contractor's information. The study
results indicate [ultraviolet oxidation] [peroxone] [_____] is capable of
meeting the criteria in paragraph Performance Requirements above. The
Contractor shall evaluate the applicability and adequacy of the
treatability studies and results provided. If deemed necessary by the
Contractor, additional studies may be performed at the Contractor's expense
to confirm the previously conducted treatability study and results. Based
on the Contractor's own interpretation of the previous studies and results,
and additional studies and results the Contractor elects to perform, the
Contractor shall provide a full scale treatment plant which meets the
requirements identified.
1.5
QUALIFICATIONS
**************************************************************************
NOTE: Designer should edit the subsequent
paragraphs and remove requirements not applicable to
the project.
**************************************************************************
1.5.1
Contractor
Contractor shall have a minimum of [3] [_____] years of experience in the
construction of water, wastewater, industrial wastewater, or hazardous and
toxic waste water treatment facilities. The Contractor shall be
responsible for installation and start-up of the AOP equipment supplied, as
well as operator training.
1.5.2
Ultraviolet (UV) Oxidation System Supplier
Equipment provided must duplicate equipment that has been in satisfactory
service for a minimum of [2] [_____] years prior to bid opening. The UV
oxidation system supplier shall be responsible for furnishing a complete
prepackaged system. The supplier need not manufacture the entire system,
but shall coordinate the selection, assembly, installation, and testing of
the entire system as specified.
1.5.3
Manufacturer's Representative
Services of a qualified manufacturer's field representative experienced in
the installation, adjustment, and operation of the equipment furnished and
SECTION 11377
Page 13