In-service test
SD-07 Certificates
Separator corrosion protection; G, [_____]
Submit written verification on the fabricator's letterhead that
surface preparation and coating application were performed in
accordance with the manufacturer's printed recommendations for the
coating system.
SD-08 Manufacturer's Instructions
Separator system; G, [_____]
SD-10 Operation and Maintenance Data
Separator system; G, [_____], Data Package 3
[
Accessory equipment; G, [_____], Data Package 3]
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA.
1.4
DELIVERY, STORAGE, AND HANDLING
1.4.1
Delivery and Storage
Inspect materials delivered to site for damage; unload and store with
minimum handling. Store materials on-site in enclosures or under
to prevent damage during periods of inclement weather, such as subfreezing
temperatures, precipitation, and high winds. Store materials susceptible
to deterioration by direct sunlight under cover and avoid damage due to
high temperatures. Do not store materials directly on ground. If special
precautions are required, prominently and legibly stencil instructions for
such precautions on outside of equipment or its crating.
1.4.2
Handling
Handle separator in such a manner as to ensure delivery to final location
in sound, undamaged condition. Take special care not to damage interior
and exterior surfaces of separator, coalescing plates, [or tubes] and
associated supports and pipe coatings or linings. Make satisfactory
repairs to damaged materials at no cost to Government. Carry and do not
drag materials.
PART 2
PRODUCTS
2.1
MATERIALS
**************************************************************************
NOTE: Insert reinforced concrete or other suitable
material if carbon steel is not acceptable. On
larger separators (e.g. flow rate greater than 3.16
L/s 50 gpm, 6 mm 1/4 inch minimum thickness for
carbon steel is recommended. Consult manufacturers'
data.
SECTION 11311