maximum application temperatures, and curing procedures. Include Materials
Safety Data Sheets (MSDS) for materials to be used at the job site in
accordance with 29 CFR 1926.59.
1.5
DELIVERY AND STORAGE
Ship, store, and handle materials in accordance with SSPC PA 1, and as
modified in this Section. Maintain temperature in storage spaces between 5
and 24 degrees C 40 and 75 degrees F, and air temperature more than 3
degrees C 5 degrees F above the dew-point at all times. Inspect materials
for damage and return non-compliant materials to manufacturer. Remove
notify the Contracting Officer. Expired materials may be returned to
manufacturer, tested, and if compliant, issued a shelf life extension.
1.6
COATING HAZARDS
**************************************************************************
NOTE: This specification Section should be used
with NFGS-01525 "SAFETY REQUIREMENTS".
**************************************************************************
Ensure that employees are trained in all aspects of the safety plan.
improperly handled. The coating manufacturer's written safety precautions
shall be followed throughout mixing, application, and curing of the
coatings. During tank cleaning, cleanup, surface preparation, and paint
application phases, ensure that employees are protected from toxic and
Comply with respiratory protection requirements in 29 CFR 1910.134. The
1.7
WORK SEQUENCE
Coat tank interior following leak testing.
1.8
JOB SITE REFERENCES
**************************************************************************
NOTE: Include any other job site related references
that might be added during design.
**************************************************************************
Make available to the Contracting Officer at least one copy each of ASTM D
3276, ASTM D 3925, ASTM D 4285, ASTM D 4417, NACE RP0188, SSPC SP COM, SSPC
SP 1, SSPC SP 7, SSPC SP 5, SSPC PA 1, SSPC PA 2, SSPC Guide 12, SSPC Guide
to VIS 1, SSPC VIS 1, and an SSPC Certified Contractor Evaluation Form at
the job site.
1.9
PRE-APPLICATION MEETING
**************************************************************************
NOTE: The Coating Manufacturer's rep may be
included for unusually large or complicated projects.
**************************************************************************
After approval of submittals but prior to the initiation of coating work,
Contractor representatives, including at a minimum, project superintendent
and QC manager, paint foreman, Contracting Officer representatives, coating
SECTION 09972