CHECK LIST
Item
Description
Appr'd/Date_
a.
Materials are handled and stored correctly.
_
____
b.
_
_____
including temperature not below 4 degrees C (40 degrees F),
and the work is protected from the elements as required.
c.
Preparation and installation is performed by qualified
_
_____
personnel using the correct tools.
d.
Adjacent areas to which EIFS is not to be applied
_
____
(such as on window and door frames) are protected with
masking tape, plastic films, drop cloths, etc.
to prevent accidental application of EIFS materials.
e.
Control, expansion and aesthetic joints are installed as
_
____
indicated or recommended. Accessories are properly
installed.
f.
Substrate is in-plane, properly attached, clean, dry, and
_
____
efflorescence.
g.
Materials are mixed thoroughly and in proper proportions.
_
____
h.
Adhesive is applied in sufficient quantity with proper-
_
____
size notched trowel.
i.
Mechanical attachments have proper spacing, layout and
_
____
fastener depth.
j.
Insulation boards are tightly abutted, in running bond
_
____
pattern, with joints staggered with the sheathing, board
corners interlocked, L-shaped boards around openings,
edges free of adhesive, and provision for joints. Gaps
are filled and surfaces rasped.
k.
Insulation adhesive must be allowed to dry (a minimum of
_
____
24-hours) prior to the application of the base coat.
l.
Reinforcing fabric mesh is properly
back-wrapped at
_
____
terminations.
m.
Reinforcing fabric mesh is fully embedded and properly
_
____
placed. Corners are reinforced. Openings are
diagonally reinforced. Mesh overlaps minimum 65 mm (2-
1/2 inches).
n.
Base coat thickness is within specified limits.
_
____
o.
The base coat/reinforcing fabric mesh must be allowed to
_
____
dry (a minimum of 24-hours) prior to the application of
the finish coat.
SECTION 07240
Page 26