CHECK LIST
Item
Description
Appr'd/Date_
p.
Finish coat is applied with sufficient number of
_
____
personnel and stopped at suitable points. Floats and
methods of texturing are uniform.
q.
All Flashings
are properly installed.
_
____
r.
All joints are properly sealed in their entire length
_
____
specified by the manufacturer.
s.
All scaffolding, equipment, materials, debris
_
____
and temporary protection are removed from site
upon completion.
Name of Inspector:________________
Signed:__________________
Date:________
3.6
CLEANUP
Upon completion, remove all scaffolding, equipment, materials and debris
from site. Remove all temporary protection installed to facilitate
installation of EIFS.
-- End of Section --
SECTION 07240
Page 27