1.3.7.3
Unit of Measure
Unit of measure: cubic meter foot.
1.3.8
Precast Concrete Units
**************************************************************************
NOTE: Repeat this bid item and its respective
subparagraphs for each bid item of precast concrete
units, renumbering the bid items appropriately.
Unit price bid items should be inserted in paragraph
UNIT PRICE BID ITEMS of Section 01270A MEASUREMENT
AND PAYMENT. When uniform thickness and
construction precast units are used, area
measurement is appropriate. If the units are not
uniform, either separate area measurements of volume
measurements should be specified.
**************************************************************************
1.3.8.1
Payment
Payment will be made for costs associated with fabricating, transporting
and erecting precast concrete units. The payment will include bearing
pads, shims, and all temporary supports required for erection. Payment for
precast units will be made at the contract price per square meter foot for:
[<Insert Type of Precast Concrete Unit(s) here>]
1.3.8.2
Measurement
Measurement of precast concrete units will be made on the basis of the
actual surface area of precast units placed, and accepted, within the
limits of work as indicated on the contract drawings. No deductions will
be made for beveled edges or space occupied by metal work, or for embedded
items.
1.3.8.3
Unit of Measure
Unit of measure: square meter feet.
1.3.9
1.3.9.1
Payment
Payment for [cement-based] [polymer-modified] concrete overlay will be made
at the respective contract unit prices per square meter yard. These
payments shall constitute full compensation for performing the work and
shall include the cost of all labor, equipment and tools, materials and
supplies required to complete the overlay work under this contract,
including surface preparation. No separate payment will be made for
bonding agents or primers, when required.
1.3.9.2
Measurement
Measurement of [cement-based] [polymer-modified] concrete overlay will be
made on the basis of the actual area of overlay placed, within the limits
of work, as indicated on the contract drawings. No deductions will be made
for voids or embedded items which are less than 0.09 square meter (one
square foot) one square foot in area.