meter yard of concrete removed. No payment will be made for concrete
removal, as such, that is in connection with items for which payment is
made as a lump sum.
1.3.1.2
Measurement
Concrete removal will be measured for payment based upon the actual volume
of concrete removed within the pay lines as indicated on the drawings.
Measurement will be made in accordance with paragraph FIELD MEASUREMENT.
No measurement will be made of concrete removal outside the pay lines shown
which is incidental to the indicated removal unless such removal is
specifically authorized by the Contracting Officer. No deductions will be
made for rounded or beveled edges or for voids or embedded items that are
either less than 0.15 cubic meters (five cubic feet) five cubic feet in
volume or 0.10 square meter (one square foot) one square foot in cross
section.
1.3.1.3
Unit of Measure
Unit of measure:
cubic meters yards.
1.3.2
Concrete Removal (Alternate)
**************************************************************************
NOTE: Repeat this bid item and its respective
subparagraphs for each bid item of concrete removal,
renumbering the bid items appropriately. Unit price
bid items should be inserted in paragraph UNIT PRICE
BID ITEMS of Section 01270A MEASUREMENT AND PAYMENT.
Where concrete removal depth is not uniform across
an area, measurement and payment should be made on a
volume basis basis, in which case the previous
paragraph should be used.
**************************************************************************
1.3.2.1
Payment
Payment will be made for costs associated with concrete removal, which
includes preparatory work, removal of concrete and embedded items, and
disposal of debris. Payment will be made at the contract price per square
meter yard of concrete removed. No payment will be made for concrete
removal, as such, that is in connection with items for which payment is
made as a lump sum.
1.3.2.2
Measurement
Concrete removal will be measured for payment based upon the actual area of
concrete removed within the pay lines as indicated on the drawings. No
measurement will be made of concrete removal outside the pay lines shown
which is incidental to the indicated removal.
1.3.2.3
Unit of Measure
Unit of measure:
square meters yards.